SWAIN HALL SCIENCE ANNEX

Introduction    (Return to List)

This project involves the construction of a 40,000 sq. ft. annex to Coastal's current Science Building which was constructed in 1980 when the student population was much smaller. The proposed annex will consist of modern laboratories and much needed faculty office space.

Current laboratories for science courses are insufficient for coursework offerings and for research in complex science areas such as Biology, Chemistry, and Physics. The labs are located in converted regular classroom spaces with insufficient air handling, inadequate water and gas supplies. Additionally, current science faculty are housed in 3 separate buildings, making interdisciplinary research and student-faculty interactions problematic. The science laboratory annex will include 20-22 science laboratories, supply spaces, and 30-35 offices for faculty.

This addition is consistent with Coastal's plans to renovate the current science building back to classroom space, and construct a new state-of-the-art science building in the future to integrate all science instruction, including marine science and computer science now in remote locations to the main campus.

Project Budget

$15,000,000

Estimated Start Date

September, 2011

Estimated Completion Date

March, 2013

Status of Project

January 16, 2013 - Jobsite progress meeting scheduled.

January 08, 2013 - Lock and key coordination meeting with Best Lock representative.

January 02, 2013 - Interior storefront frames on first floor completed. Installation of frames on second floor being installed.

November 14, 2012 - Jobsite progress meeting scheduled.

November 02, 2012 - First floor drywall installation 95% complete.

November 01, 2012 - HVAC, electrical and plumbing rough-ins on second floor.

October 31, 2012 - Site visit and follow-up inspections.

September 26, 2012 - Drywall installation of first floor scheduled to start.

September 20, 2012 - Roofing shingle installation and coverage 90% complete.

September 05, 2012 - Partial exterior brick received.

August 20, 2012 - Exterior brick installation scheduled.

August 13, 2012 - Roof deck insulation and wood panel decking 90% complete.

July 11, 2012 - Jobsite progress meeting and architect inspection scheduled.

May 02, 2012 - Jobsite meeting and architect inspection scheduled.

April 18, 2012 - Architect inspection and jobsite meeting scheduled.

April 16, 2012 - Structural steel fireproofing scheduled to start.

March 13, 2012 - Steel beam signing ceremony for Mr. Swain held.

March 12, 2012 - Mechanical rough-ins scheduled to start on ground floor. Second floor ceiling and roof structural steel components installation in progress.

March 09, 2012 - Second floor concrete pour complete.

March 05, 2012 - Mechanical installations scheduled to begin.

February 27, 2012 - Structural steel, second floor steel joists and decking installation continues.

February 22, 2012 - Jobsite meeting and architect progress inspection taken.

January 11, 2012 - Progress meeting with architect and contractor scheduled.

December 30, 2011 - West side section of the first floor concrete slab completed.

December 22, 2011 - West side perimeter block retaining walls complete.

December 16, 2011 - Backfilling underway.

December 15, 2011 - Final grade beam foundations inspected and poured on east end.

December 07, 2011 - Underground acid/waste, plumbing and mechanical piping continues on the west end of the building.

Grade beam forms are being set and steel placed in the center of the building.

November 23, 2011 - Grade beam footings are being excavated and prepared for forms on the east side and rear center of the building.

November 21, 2011 - Underground plumbing and mechanical piping began on west end of building.

November 02, 2011 - Structural steel pre-construction meeting is scheduled in conjunction with the regular construction meeting on site.

October 19, 2011 - 60% of piles have been installed.

October 04, 2011 - Pile installation began.

October 03, 2011 - Santee Cooper installed underground electrical service.

September 06, 2011 - Construction began.

August 30, 2011 - Pre-construction meeting scheduled.

July 28, 2011 - Meeting scheduled with representatives of Santee Cooper and HTC to discuss power service agreements.

June 23, 2011 - Selected contractor and posted notice of intent to award contract to Chancel Builders.

June 09, 2011 - Bid closing date.

May 05, 2011 - Pre-bid conference.

April 21, 2011 - Project advertised on SCBO.

March 21, 2011 - Architect forwarded construction document revisions and responses to OSE for final review/approval.

March 07, 2011 - Architect scheduled to forward responses to OSE for final review.

February 25, 2011 - General resolution reached on remaining comments.

February 18, 2011 - OSE and WTS met to resolve OSE comments. Approximately 80% of comments resolved.

February 01, 2011 - WTS received comments from OSE.

December 15, 2010 - WTS forwarded construction documents to OSE for final review.

September 21, 2010 - Construction documents sent to OSE for review.

September 17, 2010 - WTS to receive final construction cost estimate from Aiken Cost Consultants for review/approval.

August 24, 2010 - Lab Equipment Utilities forwarded to architect/SSOE for review.

August 13, 2010 - Met with architect to review the coordination set of drawings and upgrade scale.

June 21, 2010 - DWG/WTS/T&H continuing preparation of construction drawings.


April 02, 2010 - Final programming reviews are 85%+ complete.

March 04, 2010 - Design development phase complete. Documents submitted to Coastal Carolina University and OSE for review.

October 29, 2009 - Architects in design development phase of construction documents.

July 14, 2009 - Architects preparing Phase II contract.

June 29, 2009 - A-1 for Phase II construction approved by SC Budget & Control Board.

June 03, 2009 - A-1 for Phase II construction approved by Joint Bond Review Committee.

May 07, 2009 - A-1 for Phase II construction approved by SC Commission on Higher Education.

April 17, 2009 - A-1 for Phase II construction submitted to Commission on Higher Education for approval.

December 19, 2008 - Planning Committee continues to work with Architect on design phase.

October 27, 2008 - Architectural Selection Committee interviewed Architectural Design Teams from short list. Watson Tate Savory Architects were selected for design services.

October 09, 2008 - Architectural Selection Committee meets to short list Architectural Design Teams for interviews.

September 25, 2008 - Resumes due for Architectural Design Team.

August 25, 2008 - Advertised in SC Business Opportunities for Architectural Design Team.

August 12, 2008 - A-1 for design phase approved by Budget & Control Board.

June 17, 2008 - A moratorium on construction projects set by Budget & Control Board.


June 04, 2008 - A-1 in amount of $170,000 for design phase approved by Joint Bond Review Committee.


May 13, 2008 - A-1 submitted to Commission on Higher Education in the amount of $170,000 for design phase.
Commission on Higher Education staff approval.