PUBLIC SAFETY BUILDING

Introduction    (Return to List)

The University is planning to construct an estimated 5,000 square feet Public Safety building to include approximately 15 offices, a dispatch/communication center, a training room and locker room.

Project Budget

$1,640,000

Estimated Start Date

August, 2012

Estimated Completion Date

September, 2013

Status of Project

January 22, 2013 - Window glass installed and brickwork 95% complete.

January 09, 2013 - Electrical, plumbing and one side wall drywall rough in complete. Mechanical and brickwork in progress.

November 14, 2012 - Exterior wall studs have been erected.

November 09, 2012 - Santee Cooper has completed underground electric service.

October 24, 2012 - Final repairs completed on backflow valve.

October 19, 2012 - Fire suppression water supply installed and hydrostatic test performed.

September 11, 2012 - Site meeting with general contractor and engineering.

September 10, 2012 - Hardwoods removed and replaced at Hackler Golf Course.

August 23, 2012 - Cleared area for Public Safety building footprint.

August 21, 2012 - Construction begins.

August 14, 2012 - Pre-construction meeting.

June 26, 2012 - Bid awarded to Hanco Construction.

June 12, 2012 - Pre-bid meeting held.

May 28, 2012 - Project advertised in SCBO.

April 11, 2012 - Submitted revised plans and specs for final review to OSE.

February 27, 2012 - SMHa to have final comments addressed and submitted to OSE for final review.

February 13, 2012 - Site drawing sent to SMHa for comments.

January 17, 2012 - SMHa working on corrections to plans and specs per OSE comments.

January 12, 2012 - Received review comments from PE of OSE.

November 21, 2011 - Mailed corrected set of specs to OSE for review.

November 01, 2011 - Plans and specs submitted to OSE for review and comment.

June 28, 2011 - Castles Engineering has plans and specs complete for review.

June 08, 2011 - AIA moving forward to complete plans and specs.

April 27, 2011 - Castles Engineering providing civil engineering services.

April 14, 2011 - Exterior elevations received from AIA for review.

March 14, 2011 - Four member Public Safety Team met with Facilities Project Managers, SMHa and DWG, Inc. to review building layout plans.

March 07, 2011 - Met with AIA, and Public Safety to discuss revised layout. AIA is moving forward on completing plans and specs.

February 25, 2011 - Revised floor plans forwarded for review and final comments.

December 14, 2010 - A-1 for Phase II Construction approved by the Budget and Control Board.


October 15, 2010 - A-1 submitted to Commission on Higher Education for Phase II Construction.

October 01, 2010 - Soil testing taking place for possible relocation of building site.

May 18, 2010 - Project placed on hold.

May 06, 2010 - A-1 approved by Commission on Higher Education for Phase II construction.

March 02, 2010 - Initial meeting with IDC architects Stubbs Muldrow Herin for Phase I design.

February 23, 2010 - A-1 for Phase I design approved by Budget and Control Board.

February 10, 2010 - A-1 for Phase I design approved by JBRC.

January 07, 2010 - A-1 approved by Commission on Higher Education for Phase I design.

December 03, 2009 - A-1 submitted to Commission on Higher Education for approval of Phase I design.