TENNIS COMPLEX CONSTRUCTION
This project involves the construction of a proposed tennis complex.
This project involves a twelve court tennis complex to include lighting, coaches offices, press box, locker rooms, concessions, restrooms and equipment storage, scoreboards, PA system and bleachers.
Project Budget
$2,000,000.00
Estimated Start Date
February, 2013
Estimated Completion Date
December, 2013
Status of Project
December 13, 2012 - Reviewing CHA Sports Phase II revised proposal.
October 30, 2012 - A-1 approved by SC Budget and Control Board for Phase II Construction.
October 24, 2012 - A-1 approved by JBRC for Phase II Construction.
May 29, 2012 - A-1 approved by Commission on Higher Education for Phase II Contruction.
April 05, 2012 - Committee meeting held.
March 20, 2012 - Second programming committee meeting held.
February 20, 2012 - First programming committee meeting held.
January 24, 2012 - Standard Form of Agreement between owner and architects submitted to CHA Sports with Title IX form for review and signature.
January 04, 2012 - CHA Sports Architect/Engineering firm selected.
December 13, 2011 - Architect selection meeting scheduled.
November 18, 2011 - Meeting with selection committee to short list A/E design teams for interview.
September 23, 2011 - Received resumes from A/E design teams.
September 01, 2011 - Advertisement for Phase I design in SCBO.
August 09, 2011 - A-1 for Phase I design for construction approved by SC Budget and Control Board.
August 02, 2011 - A-1 for Phase I design for contruction approved by Joint Bond Review Committee.
May 26, 2011 - A-1 approved by Commission on Higher Education for Phase I design for contruction.
May 12, 2011 - A-1 submitted to Commission on Higher Education in the amount of $30,000 for Phase I design for construction.