PARKING/PEDWAY CONSTRUCTION

Introduction    (Return to List)

This project is for construction of three parking lots and associated sidewalk improvements to support safer bicycle and pedestrian travel. The lots will provide approximately 1,600 additional parking spaces to campus.

As directed by the University's 2010 Campus Master Plan, the new parking lots will provide additional parking capability while the University reduces surface parking within the main campus academic core (Chanticleer Drive). This will provide increased pedestrian and bicycle safety, free sites for future academic buildings to support the University's planned growth and improve greenscape areas for students use.

Project Budget

4,000,000

Estimated Start Date

May 2012

Estimated Completion Date

December 2013

Status of Project

January 14, 2013 - Digging retention ponds in Lackey lot.

January 02, 2013 - Contractor is moving organics and installing subgrade fill material in the Lackey Chapel lot.

November 12, 2012 - Plans and specs for Fire Tower Parking Lot submitted for permitting.

November 05, 2012 - Construction begins on Lackey Chapel Lot.

October 25, 2012 - Pre-construction meeting held for Lackey Chapel Lot.

September 11, 2012 - Entrance off of Highway 501 opened at Bay #3 parking.

September 10, 2012 - Drawing revisions received on Fire Tower Parking Lot.

August 28, 2012 - Pre-bid meeting held for Lackey Chapel Parking Lot.

August 14, 2012 - Lackey Chapel Lot advertised on SCBO.

August 08, 2012 - Pre-landscape meeting scheduled.

August 06, 2012 - To begin turn lane off 501.

May 14, 2012 - Bay 3 parking lot storm drainage installation complete.

March 30, 2012 - Forwarded to Mead and Hunt the complete geotechnical report for Fire Tower lot.

March 27, 2012 - Lackey Chapel Lot - Submitted plans to City of Conway for TRC MS4 review.

March 01, 2012 - Contractor for Bay #3 parking project awarded to Hardwicks Landscaping, LLC.

February 27, 2012 - Mead and Hunt presently working on preliminary drainage calculations for Fire Tower Lot.

February 24, 2012 - Received overall draft site plan for Fire Tower Parking Lot from Mead and Hunt.

February 21, 2012 - Castle Engineering presented preliminary site plan for Lackey Chapel Parking Lot.

February 09, 2012 - Bay #3 parking project advertised in SCBO.

February 08, 2012 - Received fee proposal from S&ME for soil testing on Fire Tower Parking Lot.

December 15, 2011 - A-1 for Phase II contruction approved by SC Budget and Control Board.

December 07, 2011 - A-1 for Phase II construction approved by the JBRC.

November 09, 2011 - A-1 submitted for Phase II construction to the SC Commission on Higher Education.

June 14, 2011 - A-1 for Phase I design approved by the SC Budget and Control Board.

May 23, 2011 - A-1 for Phase I design approved by the JBRC.

April 18, 2011 - A-1 for Phase I design approved by the SC Commission on Higher Education.

Pictures

No Pictures

Return to List