Phase III of the VoIP telephone migration and upgrade includes the installation of new handsets in the buildings according to the schedule below.
Monday, June 3: Arcadia Hall, Kingston Hall
Tuesday, June 4: Facilities 1-5
Thursday, June 6: Wheelwright, Indigo Hall
Monday, June 10: Jackson Student Union B, Grounds
Tuesday, June 11: Student Health Center, Sands Hall, Evergreen Hall
Thursday, June 13: Prince Building
Monday, June 17: Edwards Building
Tuesday, June 18: Edwards Building (continued)
Thursday, June 20: Garland Academic Center, Ward Training
Monday, June 24: Kearns Hall
Tuesday, June 25: Kearns Hall (if needed)
Note: Handsets will be installed in Laurel Hall once the building renovations underway are complete.